MF5001: A service firm will need to modify its staff timetable from eight-hour shifts to twelve-hour shifts. Before the change, the staff was working: Mathematical Modelling in Supply Chains Assignment, UOL, Ireland

University University of Limerick (UOL)
Subject MF5001: Mathematical Modelling In Supply Chains

Problem 1.

A service firm will need to modify its staff timetable from eight-hour shifts to twelve-hour shifts. Before the change, the staff was working eight hours a day for five days per week. After the change, for the first week, the staff will be working for three days and then will be off for four days. For the following second week, they will be working for four days and will be off for four days. This means overall the company staff will be working eighty-four hours every 2 weeks.

The highest demand period is between 5 A.M. – 7 A.M. and between 5 P.M. – 7 P.M. To accommodate this peak demand, the following twelve-hour shifts must be arranged:

  • Shift: E & E [alt], Working hours: 5 A.M. to 5 P.M., and Payment rate per week: $757
  • Shift: F & F [alt], Working hours: 7 A.M. to 7 P.M., and Payment rate per week: $841
  • Shift: G & G [alt], Working hours: 5 P.M. to 5 A.M., and Payment rate per week: $881
  • Shift: H & H [alt], Working hours: 7 P.M. to 7 A.M., and Payment rate per week: $923

The last and most desired times to commence and finish work will be used as the basis for the shift pay differentials. In any one week, staff on shift E might work Sun to Tues, while staff on shift E [alt] would work at the same times, but on Wednesday to Saturday. In the following week, staff on shift E would work Sunday to Wednesday, while staff on shift E [alt] would work the corresponding Thursday to Saturday. So, this results in scheduling the same number of staff for shift E as for shift E[alt].

Table 1 shows the firm’s staff requirement for the twenty-four-hour day. (1) Formulate this example as an LP model to determine the most economical schedule? (2) Use Microsoft Solver to solve the formulated LP model in (1).

 

Are You Searching Answer of this Question? Request Ireland Writers to Write a plagiarism Free Copy for You.

Problem 2.

A company wants to move some products (medical supplies) from Pittsburgh (Node 1) and Staunton (Node 2) to hospitals in Node 3 to Node 7. Figure 1 provides the details of this network. The shipping costs of all routes are provided below each arc. Please note that there is a vehicle capacity limitation of a maximum of 800 units for all routes. That means, for instance, no more than 800 units of products (medical supplies) can be shipped from one city to another one.

  • Formulate this problem as an LP model to determine the least costly shipping plan.
  • Solve the model in (a) using MS Solver.
  • Reformulate the model in (a) assuming that the vehicles are now changed to a different one with more capacity of up to 1000 products between any two cities.
  • Solve the model in (c) using MS Solver and compare your results with (b).

 

Get Solution of this Assessment. Hire Experts to solve this assignment for you Before Deadline.

Get Help By Expert

Are you a student in Ireland struggling with academic writing? Look no further than Irelandassignments.ie for top-quality essay help online. We understand the pressure of meeting deadlines, keeping up with academic standards, and maintaining good grades. That's why we have a team of experienced assignment writers who are experts in a wide range of academic fields, ready to help you with your academic writing needs.

Submit Your Assignment Questions & Get Plagiarism Free Answers.

Assignment-Help-Ireland.jpg

Submit Your Assignment